A good quote protects both sides. It says what is being done, for how much and by when. This guide explains what a written quote should include and how paying in stages works.
It also gives some published UK rates, so you know what is normal.
Quote or estimate?
A quote is a fixed price for a defined piece of work. An estimate is a best guess that can change. Neither is worth much unless it is written down, so ask for the figure and the description on paper or in an email.
What a written quote should include
- Your name and address and the builder's name and contact details
- A description of the work, room by room or stage by stage
- The price, and whether it includes materials
- Anything that is left out, such as plastering, painting, a skip or scaffolding
- The start date and an estimated length in weeks
- How and when you will be asked to pay
- How changes will be priced if you ask for extra work
Hourly, daily or fixed price
The extension cost guide gives £20 to £35 an hour as a builder's average, and notes that bigger jobs are usually priced by the day or as a fixed rate. Its garden wall guide shows a bricklayer's average day at £150 to £200 and a labourer's at £70 to £100.
A fixed price suits most homeowners, because you know the total before the work starts. Hourly or daily rates suit small repairs or jobs where the extent of the problem is unknown until something is opened up. If a builder offers a day rate on a big job, ask for a rough total and a limit.
Staged payments
On larger jobs it is normal to pay in stages tied to finished work, not to dates. A simple pattern might be a small payment to book the work, then payments when the foundations are in, when the walls and roof are up, when the first fix is done, and a final payment when you are happy with the finished job.
Keep back a small final amount until everything is finished and any snags are put right. Write the stages in the quote so that nobody has to guess.
Deposits
Some builders ask for a deposit to cover the cost of materials. That is not unusual, but it should be a modest share of the price and written down. A request for most of the money at the start is a warning sign. Pay by bank transfer or another method that leaves a record.
Extras and changes
Old houses can turn up surprises: rotten timber, a wall with no foundations, wiring that has to be replaced. Ask how the builder will tell you and agree the price before extra work begins. Keep a small reserve in your budget for it.
Compare like with like
When you have two or three quotes, lay them side by side. Check that each one covers the same work and the same materials. A quote that is much lower may have left something out, and one that is much higher may include things you do not need.
Common questions
How much is a builder?
The extension cost guide gives a builder's average as £20 to £35 an hour. Large jobs are mostly sold as a fixed price. The only way to know what your job costs is to have it looked at.
A clear quote saves arguments later
Most disputes about building work start with something that was never written down. Put the price, the work and the payment stages on paper before the first day.